Realization of 43km of gutters in Fada N’Gourma: The physical execution rate of the works varies between 50 and 70%

Recent Post

Advertisement

A control mission of the construction site of 43 kilometers of gutters in the city of Fada N’Gourma went to soak up the progress of the work, Thursday, March 23, 2023 According to the observation made by the said mission, from one company to another, the rate of physical execution of the work varies between 50 and 70%.

As part of the implementation of the Emergency, Territorial Development and Resilience Project (PUDTR), the city of Fada N’Gourma benefits from a linear of forty-three (43) km of water drainage channels storm drains as well as a crossing culvert.

Led by the Infrastructure Works Agency of Burkina (AGETIB), this emblematic sub-project mobilized 8 companies.

3- A gutter in masonry of solid blocks made by the HIMO method in sector 10.

After the effective start of the works in October 2022, all the sites are progressing well, according to the observation of a control mission, Thursday March 23, 2023. The rural engineering engineer of the AGEIM IC design office, Pascal Ouédraogo , also head of this mission, indicated that, from one company to another, the rate of physical execution of the work varies between 50 and 70%.

Figures which, according to him, announce the end of the work in about a month. And if this sub-project is completed in accordance with the indicated deadline, the population will be able to welcome the rainy season with more serenity, continued Pascal Ouédraogo. It is, precisely, for the PUDTR, to offer a healthy and secure living environment to the population.

1- A 1.5km long primary canal linking sectors 10 and 11.

In addition, the sub-project for the construction of gutters in the city of Fada N’Gourma has promoted the creation of a multitude of jobs for young people through the High Intensity of Labor (HIMO) method, indicated Mr. Ouedraogo.

However, it should be noted that the works caused some disruption of road traffic and the facilities of the National Water and Sanitation Office (ONEA). As a result, some areas of the city are facing water cuts.

4- The work will be completed in about a month if there are no major constraints, said the head of the mission, Pascal Ouédraogo.

For these regrettable inconveniences, the head of mission Pascal Ouédraogo called on the population to be indulgent.

As a reminder, the PUDTR was born out of the will of the Burkinabe government with the support of the World Bank to improve the inclusive access of communities (including IDPs) in the targeted areas to infrastructure and essential social services. In short, it is a question of contributing to the resilience of the populations of the areas hard hit by insecurity.

Source: Burkina Information Agency